I tacked the front lip and rear wall to the floor. The front lip was a BEAR to get lined up. I then removed the bracing I installed and measured everything again. Nothing moved during the floor install which made me very happy. Next, I began to replace the inner kick panels of the cab. I did not spot weld the tunnel in place as I suspect that later I will need to modify it to clear the automatic transmission I intend on installing. The information given on the reproduction floors state that modification will be needed for an automatic transmission and I bet that the tunnel is too low. The panel installation is going slowly but smoothly. I often wonder how many hours it would take an experienced shop to do these things. I am glad I have started tracking hours. It really is illuminating on how much time goes into these old girls.

I also tore the front clip apart so I could lighten the fender load when I go to check door alignment. I installed the core support on the frame loosely in preparation for this. I need to get a couple large washers for the bolts that go through the frame mounts.

Cab hours: 25

Total: 37.5



https://photos.app.goo.gl/RNRkfM8rKwrjHdGX9

Last edited by Fox; 03/22/2019 4:26 AM.

1970 Chevrolet C10
Grandpa's -- My first truck -- In progress to shiny
Follow the build in the Project Journal
1950 Chevrolet 1-Ton Dually
"Ole Red Girl"
In the Stovebolt Gallery
More pictures here
1951 GMC 9430 1 ton dually--Shiny! | 1972 Chevrolet C20- Rusty- the puzzle box lid for the C10 | 1962 AMC Rambler American- my wife's
Parts trucks-
1951 GMC 9300 | 1951-GMC 9430 | 1951- Chevrolet 1300