I meant setting the rebar 4 inches into the slab. I have the rebar spaced at 16" around the parameter and will fill each core with concrete before setting the J bolts for the sill plates.
I think setting the blocks flush with edge makes sense for drainage. I don't think a horizontal rebar will be necessary.