The rule with fuses and breakers is
Everything downstream must blow before upstream
If all your fuses add up to say 70 amps
Then up stream must be over 70 amps with margin
There should not be a situation where you maximally load the network and blow a high up fuse or breaker without an intermediate legitimate fault or simply all downstream loads near but not over their individual limits.
It’s not complicated once you get the core idea and I maybe explaining it poorly, so I apologize in advance if I make no sense.